Read MoreMCA Kosovo has identified the need to dislocate the existing 10(20) kV network segment, to proceed with the development of the planned Battery Energy Storage System (BESS) project. The current medium-voltage network is located within the perimeter designated for the construction of BESS infrastructure, which could challenge the civil and electrical works, and installation of the main system equipment. Hence, the relocation of the 10(20) kV network is a necessary intervention to ensure the required technical space and to comply with electrical safety distances and standards.
In addition to the technical aspect, the network relocation process is directly linked to administrative procedures. As a starting point, a preliminary permit was granted, constituting the basic documentation required to proceed with the relocation of the energy infrastructure.
The completion of the relocation and the issuance of the preliminary permit created the necessary conditions for the uninterrupted continuation of the BESS project, ensuring safe development in accordance with legal and technical requirements in the Municipality of Istog.
We marked the second anniversary of the MCC-Kosovo Compact entry-into-force. This is a $236.7 million agreement, reached between the United…
Read More
MCA-Kosovo and the University of Prishtina are advancing the operationalization of the Centerfor Energy Skills and Innovation (CESI), a key…
Read More
The Millennium Challenge Account-Kosovo (MCA-Kosovo) and the University of Prishtina “Hasan Prishtina” have entered a strategic partnership aimed at strengthening…
Read More